By the time an occupancy permit is issued, a long list of things should already exist: a defensible interim budget, insurance on the completed building, a bank account and accounting structure, a configured owner portal, a document package for closing, and a manager who already knows the building. Assembling those in the last fortnight is how handovers go badly.
Klein is engaged on most projects six to nine months before occupancy. That is not us padding a scope — it is the point at which budget comparables, insurance appraisal and document preparation genuinely need to begin if they are going to be ready.
A first-year budget that is too low is not a favour to anybody. It makes the sales pro forma look good and then produces a fee increase in year two, an angry first AGM and a reputation that follows the next project. We build interim budgets from comparables in buildings of similar age, size and amenity — and we will tell you when a number is optimistic.
Course-of-construction cover ends; the building needs its own policy, placed on a current appraisal, before anyone takes possession. BC strata insurance has been a difficult market for several years and deductibles on water damage in particular need to be understood by the first council rather than discovered by them.
The corporation needs a bank account, a chart of accounts, a collection mechanism and a portal that works on the day the first owner moves in. Set up afterwards, the first two months of records are reconstructed rather than recorded, and it shows at the first audit.
Every purchaser receives a package. Done well, it answers the questions they would otherwise ring you about: who manages the building, how to pay, what the bylaws say, how to book the elevator, what the warranty covers and who to call at midnight.
Counting backwards from the occupancy permit.
Engagement, comparable analysis and the first draft of the interim budget. Appraisal commissioned. This is also when we flag anything in the sales material that the operating numbers will not support.
Insurance placed. Bank accounts and accounting structure established. Portal configured. Document package drafted and sent for your review.
Service contracts tendered or novated. O&M manuals, as-builts and commissioning records collected. Keys, fobs and access systems handed over. Welcome packages produced.
Closings begin, portal goes live, first fees or rents collected. The engagement continues into strata turnover or into rental lease-up, depending on the project.
Six to nine months before occupancy for a strata project. Earlier if the building has unusual amenity, a phased structure or an air space parcel, because the budget and insurance work takes longer in all three cases. Rental projects can start later on the operations side but need to start earlier on marketing — see lease-up.
Yes, and we will review it and tell you honestly what we think. Where we disagree we will say so in writing, with the comparables behind our view. What we will not do is sign off a budget we think is indefensible, because we are the ones who have to explain it at the first AGM.
Normally a fixed fee for the handover scope rather than a percentage, scaled to unit count and complexity, plus third-party costs such as the appraisal at cost. Quoted per project. The ongoing management agreement is priced separately and does not depend on using us for handover.
No. Developer services can be a standalone engagement, and some developers use us for handover and run a competitive process for ongoing management afterwards. We would rather win that on merit. In practice most projects continue with us, because by occupancy we know the building better than anyone bidding cold.
Both are handled, and both need the budget and governance work started earlier. Phased developments bring disclosure obligations and the question of how shared facilities are funded across phases; air space parcels bring a reciprocal easement agreement that governs cost sharing and usually needs careful reading before any budget is built on it.
Most of it, minus the strata governance. You still need a defensible operating budget, insurance on the completed building, accounting and portals live, and the handover documentation collected. What replaces the strata work is lease-up.
“Shawn Lu has truly been an amazing property manager. As a tenant, I've received tremendous support ensuring our move-in was smooth and that the property is managed and maintained efficiently. Shawn has gone above and beyond — truly the best out there.”
“Josh helps me manage my rental properties and is reliable and responsive. He’s been great at finding good tenants and the ongoing management, making my life a lot easier while I’m overseas.”
“Josh knows his business inside and out. He has been my property manager for several years. He is always quick to respond, provides solutions and accurate and timely reporting. His tenant searches are thorough and placements have been highly successful. I highly recommend his service, you are getting one of the best in the industry and you won’t regret it.”
Request a proposal
Tell us the address, the unit count and the occupancy date. We will come back with a scope and a fee for the handover work.